top of page
Shoshone-Bannock Tribes
TRANSPORTATION
D E P A R T M E N T
2017 Projects
Little Indian Road Reconstruction
Nov 2017
Little Indian Road reconstruction project finished Nov 16, 2017. Some of the main concerns were the road in certain area was starting to sink due to the Main Fort Hall Canal, water getting in the base and softening the road. To fix those problems the road was moved away from the canal and in those areas small culverts and drain fields were add to stop or divert water from getting in the road base.
Philbin Road Crack Sealing
Sept 2017
Started at the intersection of Beach-Marshall and Ariwite & Philbin Road heading south toward Sheepskin Road. The crack seal is to prevent water from getting under the road, it will also extend the life of the road.
bottom of page